Project Timeline and Milestone Deliverables


Last Update/Revision: 12 Nov 2011


26 Sept - 14 Oct [Research Stage]

  • Evidence of market research
  • Compilation of reference material
  • Annotated bibliography/reading list
17 Oct - 28 Oct [Feasibility Stage]

  • Review and discuss proposal idea with peers
  • Ensure I am happy with my choice of project and happy to submit/move forward with it
31 Oct - 18 Nov [Concept Stage]

  • Draft high-level project game concept
  • Format blog to suit chosen theme
  • 4 Nov [MILESTONE] Final project proposal submitted - Approval needed
  • 18 Nov [MILESTONE] Game Concept Document - Sign off needed
21 Nov - 16 Dec [Dedicated Flash Practice/Learning Stage]

  • Acquire basic Flash/ActionScript skills and understanding
  • Attend Flash/MMF session (day TBC)
  • Confirm that all desired mechanics are possible and achievable prior to commencing final design and development
19 Dec - 20 Jan [Design Stage]

  • Work on and clarify/tighten the game design, mechanics and features so they are understood in more detail, ready to go into production with no ambiguity
  • Prepare slides and talk for presentation
  • 13 Jan [MILESTONE] Design Document
  • WC 16 Jan Date TBC [MILESTONE] Seminar Presentation

23 Jan - 2 Mar [Code Development Stage]

  • Build game prototype in Flash (ensure all core mechanics are implemented and functioning, using only placeholder art)
  • 2 Mar [MILESTONE] Vertical Slice - Sign off needed

5 Mar - 30 Mar [Art & Audio Development Stage]

  • All art and audio requirements of the game to now be implemented into Flash
  • 30 Mar [MILESTONE] Alpha Version - Sign off Needed

2 Apr - 13 Apr [Testing & Feedback Stage]

  • Collect user feedback from playtesters by getting them to fill in questionaires
  • Fix any bugs found and make changes if deemed necessary according to feedback
  • 13 Apr [MILESTONE] Beta Version - Sign off needed
16 Apr - 27 Apr [Contingency Time]

  • Evaluate game
  • Add any desirable extras/final polishes if still wished and time remains to do so
  • Prepare game files so they are ready for hand-in and check it works
  • Organise accompanying game assets and documentation to submit with game
  • 27 Apr [MILESTONE] Formal Submission of Final Artefact/ Project End


Note: Work to be negotiated with my specialist tutor (Chris Janes) at regular meetings (TBA) where we will discuss and make adjustments to the work based on advice, feedback and identified concerns.